RCDDV14.1 practice question 27 of 35

Which two of the following items should be considered for inclusion in a comprehensive working outline of a SoW? (Select two options.)

Full set: 320 questions
Answer options
A: Schedule Correct answer
B: Contract administration
C: Legal matters
D: Technical considerations Correct answer
E: Financial matters
Correct Answer:
A. Schedule; D. Technical considerations
Explanation

A comprehensive Scope of Work (SoW) outline focuses on what will be done and when. BICSI lists “schedule (milestones, completion dates)” and “technical considerations (codes, performance criteria, material requirements)” as core elements. Contract administration, legal clauses, and finance are addressed in other project documents (e.g., the contract agreement and general conditions), not the SoW itself.

Why Incorrect

B. Contract administration language belongs in the contract, not the SoW.
C. Legal matters are handled in the contract terms and general conditions.
E. Financial matters (pricing, payment) are covered in the bid form or contract, not the SoW outline.

References

1. BICSI TDMM, 14th ed., Ch. 2 “Project Documentation,” §2.3.2, p. 2-11 lists schedule and technical considerations as primary SoW headings.

2. MIT OpenCourseWare, “Project Management for Construction,” Lecture 5 notes, p. 5-4 (distinguishes SoW from contractual/legal sections).