RCDDV14.1 practice question 22 of 35

A program is in its execution phase when a component project manager suggests a potential change that could increase the financial benefit of the program. The program manager is hesitant to submit a change request, as it would extend the program schedule and require a scope change. To whom should the change request be presented?

Full set: 320 questions
Answer options
A: The program governance board Correct answer
B: The program customer
C: The program management office (PMO)
D: The protect governance board
Correct Answer:
A. The program governance board
Explanation

The program governance board is the ultimate decision-making body for a program. It is responsible for providing strategic direction, oversight, and approving significant changes that affect the program's scope, schedule, budget, or expected benefits. A change that increases financial benefit but also extends the schedule and alters scope is a strategic decision. Therefore, it must be presented to the program governance board for review and approval. The program manager's role is to analyze the change and present it to the board with a recommendation.

Why Incorrect

B. The program customer is a key stakeholder whose input is vital, but they do not have the final authority to approve strategic program changes.
C. The Program Management Office (PMO) provides support, standards, and oversight but typically does not have the authority to approve major scope or schedule changes.
D. A project governance board oversees a single project; this change impacts the overall program and thus falls under the purview of the higher-level program governance board.

References

Project Management Institute. (2017). The Standard for Program Management (4th ed.). Section 2.4.1 Program Governance, p. 22. "Program governance includes the processes and procedures for exercising authority, for making decisions, and for providing oversight of the program."

Project Management Institute. (2017). The Standard for Program Management (4th ed.). Section 5.5 Program Change Management, p. 84. "The program manager is responsible for managing program changes in accordance with the program change management plan and presenting proposed changes to the program governance board for approval."