RCDDV14.1 practice question 20 of 35

A program manager recognizes that a successful resource being used in project A could also be used in project B. What should the program manager do first to leverage the utilization of this resource?

Full set: 320 questions
Answer options
A: Assign project A's resource to project B
B: Reassign the resource to project B after protect A ends
C: Prioritize the resource to optimize their use across both projects A and B Correct answer
D: Mitigate risk by leveraging other resources in project A
Correct Answer:
C. Prioritize the resource to optimize their use across both projects A and B
Explanation

Optimal utilisation of a high-performing resource across multiple components requires integrated prioritisation at the program level. The program manager should balance the individual’s availability and the criticality of tasks in both projects, then allocate the resource where overall program value is maximised. Prioritising before unilaterally reassigning respects both project managers’ needs and adheres to program resource optimisation practices.

Why Incorrect

A. Unilaterally moving the person ignores project B needs analysis and may jeopardise project A deliverables.
B. Waiting wastes an immediately valuable resource and may delay project B.
D. Shifting other resources in project A does not address leveraging the proven high performer across both efforts.

References

1. PMI – The Standard for Program Management, 4th ed., §7.4 “Optimize Program Resources”, pp. 79-80.

2. MIT OpenCourseWare – 15.761 “Introduction to Operations Management”, Lecture 6 (resource leveling concepts).

3. Andersen, E.S. et al. (2015). “Resource Allocation in Multi-Project Environments”, International Journal of Project Management, 33(1), pp. 122-130. https://doi.org/10.1016/j.ijproman.2014.04.004