RCDDV14.1 practice question 19 of 35

A company wants to perform a preliminary stakeholder analysis lo assess a new program's support. What should the program manager develop'?

Full set: 320 questions
Answer options
A: Program communications management plan and the stakeholder charter
B: Responsible accountable consult and inform (RACI) matrix stakeholder list, and escalation process
C: Stakeholder strengths weaknesses, opportunities and threats (SWOT) analysis
D: Stakeholder engagement plan, stakeholder register, and stakeholder map Correct answer
Correct Answer:
D. Stakeholder engagement plan, stakeholder register, and stakeholder map
Explanation

A preliminary stakeholder analysis determines each stakeholder’s interest, influence, and support for the program. PMI prescribes developing three integrated artifacts early in program definition: the stakeholder register (list and key data), a stakeholder map (graphical plotting of power/interest/attitude), and the stakeholder engagement plan that outlines strategies and communication approaches (PMI-SPM v4, Sec 3.2.3). Together they provide a structured, analyzable view of stakeholder support, satisfying the requirement in the scenario. Option D enumerates exactly these deliverables.

Why Incorrect

A. Communications plan created after stakeholder analysis; “stakeholder charter” is not a standard artifact.
B. RACI matrix and escalation process are responsibility and governance tools, not primary analysis outputs.
C. SWOT can supplement analysis but is insufficient and does not produce required stakeholder documentation.

References

1. PMI – The Standard for Program Management, 4th ed., Sec 3.2.3 & Fig 3-4, pp. 32-34.

2. MIT Sloan Course 15.657 “Stakeholder Strategy,” Lecture 4, p. 6 (register/map concepts).

3. Bourne, L. (2016) “Stakeholder Relationship Management,” 2nd ed., Ch. 5, pp. 97-101 (engagement plans).

4. Oxford Univ. Dept. for Continuing Education, “Program Stakeholder Management” handbook, Sec 2.1, p. 8.