RCDDV14.1 practice question 18 of 35

A global financial system is being delivered by the program learn to allow access from anywhere in the world Following a new cross-border regulation…

Full set: 320 questions
A global financial system is being delivered by the program learn to allow access from anywhere in the world Following a new cross-border regulation applying to privacy of local banking data accessed from abroad, the CEO of the bank requests that an external audit be conducted lo validate compliance with this new regulation. This event, which was not anticipated al this phase of the program, will generate additional work tor the program learn. This effort Is not included in the current program roadmap and benefits delivery plan What immediate actions should the program manager take?
Answer options
A: Negotiate with the CEO in an attempt to avoid the audit.
B: De-scope the capabilities of the system to not allow access from abroad
C: Accept the risk of the audit and continue the program as planned
D: Assess the impact of the audit and potential remediation on the program Correct answer
Correct Answer:
D. Assess the impact of the audit and potential remediation on the program
Explanation

When an unanticipated event like a mandated audit occurs, it represents a significant change or issue. The standard process in program management governance requires the program manager to first conduct a thorough impact assessment. This analysis evaluates the effects on the program's scope, schedule, budget, resources, and its ability to deliver the planned benefits. This data-driven assessment is crucial for enabling the CEO and the governance board to make an informed decision on how to incorporate the new work, rather than making a premature decision based on assumptions.

Why Incorrect

A: Negotiating to avoid a CEO-requested compliance audit is inappropriate and lacks the necessary data from an impact assessment to be effective. B: De-scoping is a significant strategic decision that should only be considered after an impact analysis demonstrates it is the best course of action. C: A direct request from the CEO is a directive to be managed, not a risk to be passively accepted and ignored.

References

Project Management Institute. (2017). The Standard for Program Management (4th ed.). Section 5.5, Program Change Management. This section details the process for managing changes, which begins with assessing the impact of a change request on all program aspects.

Project Management Institute. (2017). The Standard for Program Management (4th ed.). Section 7.3.2, Program Monitoring and Control Activities. This section emphasizes the need to analyze issues and changes to understand their effect on the program before taking corrective action.