RCDDV14.1 practice question 17 of 35
A three-year program using vendor contracts, incorporating related projects, and each with specific stakeholders is coming to an end What should be completed first to close all appropriate contracts?
Full set: 320 questionsThe first step in the contract closure process is to verify that all work and deliverables are complete and satisfactory according to the contract terms. This involves a thorough assessment to ensure all conditions have been met by the vendor. Only after this verification can the program formally certify completion, conduct final audits, or close out the administrative aspects of the contract. This assessment confirms that the program has received what it paid for before finalizing payments and releasing the vendor.
A. Certify contract completion: This is a subsequent step that can only occur after assessing that all conditions have been met.
B. Conduct a procurement audit to review the procurement process: This is a lessons-learned activity performed during closure, but after verifying the contract's deliverables are complete.
D. Review contract management plan for completeness: This plan should have been reviewed and followed throughout the program, not as a first step for closure.
Kerzner, H. (2017). Project Management: A Systems Approach to Planning, Scheduling, and Controlling (12th ed.). Wiley. As referenced in various university-level project management curricula, Chapter 18, "Project Closeout," outlines that verification of deliverables against contract requirements is a primary step in the closure process (pp. 630-632).
Project Management Institute. (2017). A Guide to the Project Management Body of Knowledge (PMBOK® Guide) (6th ed.). Section 12.4, "Control Procurements," describes the process of managing contracts, which includes verifying that all work is completed satisfactorily before formal closure. This standard is a foundational text in university project management courses worldwide.
Keep practicing
Take the free RCDDV14.1 practice test
Ten exam-style questions with answers and explanations, plus the exam facts and study guides.
More questions
Other RCDDV14.1 practice questions
- Question 1A large international manufacturing company is centralizing its IT which is currently spr…
- Question 2Which of the following terms is often used to describe two parallel paths that have ident…
- Question 3An organization initiates an innovation program to deliver exceptional performance and be…
- Question 4The program manager wants to ensure that a program contributes to shareholder value. The …
- Question 5The chief executive officer reminds a program manager that a program must deliver a 30% r…
- Question 6An initiative involves the development of new technology and leverages existing technolog…