RCDDV14.1 practice question 16 of 35

To create market advantage, a program sponsor requests accelerating the implementation of a new manufacturing process that is based on a recently improved system component. The program manager is concerned that the delivery of some program goals could be jeopardized. What should the program manager do?

Full set: 320 questions
Answer options
A: Document the concerns that program goals may be affected and present at the next program governance board review meeting for guidance and actions to be taken.
B: Advise the program sponsor that the program will continue and follow the program management plan, unless the change control board (CCB) has approved changes to the plan Correct answer
C: Work with the project managers of the affected components to implement fast tracking and update the resource management plan accordingly
D: Evaluate critical success factors and key performance indicators (KPIs) to monitor benefits throughout the program's life cycle
Correct Answer:
B. Advise the program sponsor that the program will continue and follow the program management plan, unless the change control board (CCB) has approved changes to the plan
Explanation

The sponsor's request represents a significant change to the program's scope and execution strategy. According to formal program management governance, any such change must be managed through a defined change control process. The program manager's immediate responsibility is to uphold this process. Advising the sponsor that the current plan remains the baseline until a formal change is evaluated and approved by the Change Control Board (CCB) is the correct professional and procedural response. This ensures that the impacts on all program goals, resources, and benefits are properly assessed before a decision is made.

Why Incorrect

A. While presenting to the governance board is part of the process, the immediate action is to inform the sponsor of the required change control procedure.
C. Implementing fast-tracking without a formal impact analysis and approval is unauthorized and irresponsible, especially when goals are known to be at risk.
D. Evaluating KPIs is an ongoing monitoring activity, not the specific action required to manage a significant change request from a sponsor.

References

1. Project Management Institute. (2017). The Standard for Program Management (4th ed.). Section 5.5, Program Change Management. "Program change management is the process by which changes to the program are identified, assessed, approved, and incorporated into the program." (p. 98).

2. Project Management Institute. (2017). A Guide to the Project Management Body of Knowledge (PMBOK® Guide) (6th ed.). Section 4.6, Perform Integrated Change Control. This process is used to review, approve, and manage change requests.