RCDDV14.1 practice question 15 of 35

A program experiences issues during execution. The stakeholders are concerned and the program manager feels pressure to act on these issues. What tool should be used to trigger a planned response when receiving lower than expected results'? Key performance indicators

Full set: 320 questions
Answer options
A: Benefits management plan Correct answer
B: Communications management plan
C: Ishikawa diagram
Correct Answer:
A. Benefits management plan
Explanation

Key Performance Indicators (KPIs) are the primary tool for monitoring program health against established baselines. They are defined with specific thresholds that, when breached by lower-than-expected results, automatically trigger a planned response or management action. This mechanism ensures that deviations from the plan are addressed systematically. The KPI serves as the early warning system that initiates corrective or preventive actions as outlined in the program management plan.

Why Incorrect

B. Benefits management plan: This is a strategic document for benefit realization, not a tool for triggering real-time operational responses to performance issues.
C. Communications management plan: This plan governs how information is shared but does not itself trigger responses based on performance data.
D. Ishikawa diagram: This is a root-cause analysis tool used to investigate a problem after it has been identified, not to trigger the initial response.

References

Project Management Institute. (2017). The Standard for Program Management – Fourth Edition. Section 5.4.2, Program Monitoring and Control. This section details the use of performance metrics (KPIs) to compare actual performance against plans, which is the basis for triggering corrective actions.