RCDDV14.1 practice question 14 of 35

A program includes the development and shipping of 12 million product units over the next year. However, one program supplier has a history of overestimating its planned volume, which puts the product launch at risk What should the program manager do to monitor and control the supplier?

Full set: 320 questions
Answer options
A: Use expert judgment and update the program procurement plan
B: Seek stakeholder approval of program procurement management activities
C: Examine performance reports, audits, and inspections Correct answer
D: Review proposal evaluation criteria, risk analyses, and mitigation strategies
Correct Answer:
C. Examine performance reports, audits, and inspections
Explanation

Program procurement control relies on objective surveillance of the seller’s actual results. The Standard for Program Management prescribes use of performance reports, audits, and inspections to verify compliance and trigger corrective action, allowing early detection of the supplier’s volume-planning variance.

Why Incorrect

A – Expert judgment may refine the plan but does not provide ongoing, objective monitoring data. B – Stakeholder approval authorises activities; it does not constitute a control technique. D – Evaluation criteria and mitigation strategies are input to selection, not tools for in-flight control.

References

1. PMI, The Standard for Program Management, 4th ed., Sec. 3.5.2 “Control Program Procurement”, pp. 92-94 – lists performance reports, audits, inspections as primary control tools.

2. Kerzner & Saladis, Program Management for Improved Business Results, 2nd ed., Ch. 12, pp. 276-277 – highlights supplier performance reviews for risk containment.