RCDDV14.1 practice question 13 of 35

A program manager takes over a global program from another program manager. Upon arriving on- site, the program manager immediately sees that stakeholders are upset because of a lack of updates and communications about the program. What should the program manager do first?

Full set: 320 questions
Answer options
A: Review the program governance plan and communication log
B: Review the program communications management plan and stakeholder register Correct answer
C: Review the stakeholder engagement plan and stakeholder matrix
D: Notify the executive sponsor and update the program issue tog
Correct Answer:
B. Review the program communications management plan and stakeholder register
Explanation

The first action is to understand the communications framework that was previously agreed to and the audiences involved. The program communications management plan defines required information, frequency, media, and responsibilities, while the stakeholder register lists who must receive the information. By reviewing these two documents the new program manager can quickly identify gaps that created the present dissatisfaction and determine next steps before taking corrective or escalatory action.

Why Incorrect

A. Governance plan/communication log show past activity, not the baseline expectations that must first be understood.
C. Stakeholder engagement plan focuses on strategies to raise engagement after communications needs are known.
D. Escalating without first analysing root-cause violates PMI escalation principles and may worsen trust.

References

1. PMI – The Standard for Program Management, 4th ed., §8.1.3 “Program Communications Management Plan Contents”, pp. 91-92.

2. PMI – The Standard for Program Management, 4th ed., §8.1.2 “Stakeholder Register”, p. 90.

3. Kerzner, H. (2017). Project Management: A Systems Approach, 12th ed., Wiley, §19.2.1 (communication baselines).

Scroll to Top