RCDDV14.1 practice question 12 of 35

The program sponsor requests a weekly performance report. The tools and techniques to monitor and control program performance include which of the following?

Full set: 320 questions
Answer options
A: Program management performance variances business criteria reweighting, root cause identification, and statistical sampling
B: Interviewing, SWOT analysis, run chart and matrix-based charts
C: Earned value management financial reporting systems, performance measurement techniques and program management information systems Correct answer
D: Delphi technique, scatter diagram. Pareto chart, and organization charts
Correct Answer:
C. Earned value management financial reporting systems, performance measurement techniques and program management information systems
Explanation

Monitoring and controlling program performance relies on integrated information systems that provide objective, quantitative data. PMI identifies earned value management (EVM), performance-measurement baselines, financial reporting systems, and program management information systems (PMIS) as primary tools and techniques (PMI-SPM v4, Sec 7.3.1). These instruments allow variance analysis, forecasting, and trend evaluation required in weekly sponsor reports. The elements listed in option C exactly match those prescribed techniques; the other options mix unrelated or qualitative tools not cited for routine performance control at program level.

Why Incorrect

A. Root-cause and sampling are quality/decision tools, not primary program performance control systems.
B. Interviewing, SWOT, run charts are situational analysis techniques, inadequate for ongoing quantitative control.
D. Delphi, scatter, Pareto, org charts are facilitation/visual aids, not integrated performance control systems.

References

1. PMI – The Standard for Program Management, 4th ed., Sec 7.3.1 & Table 7-2, pp. 115-117.

2. Kerzner, H. (2017) Project Management: A Systems Approach, 12th ed., Ch. 15, pp. 675-678 (EVM & PMIS tools).

3. Stanford Online “Advanced Project Management,” Week 5 notes, p. 3 (“Program performance measurement techniques”).

4. GAO Cost Estimating & Assessment Guide (2020), Ch. 19, pp. 489-491 (EVM for program oversight).