RCDDV14.1 practice question 11 of 35
A new program is comprised of four component projects. The program manager must assign project managers to each of the tour projects. There are eight potential project managers to consider. What should the program manager do before assigning the project managers?
Full set: 320 questionsThe most critical initial step in assigning personnel is to ensure a proper fit between the project's requirements and the individual's capabilities. The program manager must first analyze the specific needs of each of the four component projects—such as technical complexity, stakeholder environment, and risk level. Subsequently, they should evaluate the skills, experience, and competencies of the eight potential project managers. This matching process is fundamental to setting each project up for success and is a core principle of resource management within the project management framework.
A. Budgetary constraints are important but are typically considered after determining the best fit, as the primary goal is project success, not just cost containment.
B. Performance feedback is a valuable input for the evaluation process (Option C), but it is not the first or most comprehensive action to take.
D. While understanding career aspirations is good for long-term team management, it is secondary to matching immediate project needs with proven skills.
1. BICSI. (2020). Telecommunications Distribution Methods Manual (TDMM) (14th ed.). Chapter 3, Project Management, Section: Assembling the Project Team. The manual emphasizes the importance of selecting team members, including project managers, based on the skills and experience required for the project's specific tasks.
2. ANSI/BICSI 007-2020, Information Communication Technology Design and Implementation Practices for Intelligent Buildings and Premises. Section 4, Design, and Section 5, Implementation. These sections implicitly require that personnel with appropriate qualifications are assigned to specific project phases, reinforcing the need to match skills to project needs.
Keep practicing
Take the free RCDDV14.1 practice test
Ten exam-style questions with answers and explanations, plus the exam facts and study guides.
More questions
Other RCDDV14.1 practice questions
- Question 1A large international manufacturing company is centralizing its IT which is currently spr…
- Question 2Which of the following terms is often used to describe two parallel paths that have ident…
- Question 3An organization initiates an innovation program to deliver exceptional performance and be…
- Question 4The program manager wants to ensure that a program contributes to shareholder value. The …
- Question 5The chief executive officer reminds a program manager that a program must deliver a 30% r…
- Question 6An initiative involves the development of new technology and leverages existing technolog…