RCDDV14.1 practice question 10 of 35
Which two of the following documents MUST be submitted by the communication's project contractor for review and approval? {Select two options.)
Full set: 320 questionsDuring a communications project, the contractor must submit specific documents for formal review and approval to ensure compliance with the contract specifications. Shop drawings are submitted before installation to detail the contractor's plan for assembly and installation, requiring approval to proceed. Test reports are submitted after installation is complete to provide objective evidence that the installed system meets the specified performance criteria. Approval of these reports is typically required for project acceptance and closeout.
C. Cost summary: This is a financial document related to bidding or change orders, not a technical submittal for design compliance review during construction.
D. Site survey: This is typically performed during the design phase, often by the designer, to gather information. It is not a document submitted by the contractor for approval during construction.
E. Request for information (RFI): This is a formal question from the contractor to the designer to clarify ambiguities in the contract documents; it is a request, not a submittal for approval.
1. BICSI, Telecommunications Distribution Methods Manual (TDMM), 14th Edition. Chapter 3, Project Management, Section: Construction Administration. This section describes the submittal review process, identifying shop drawings as a key item for review before work begins.
2. BICSI, Telecommunications Distribution Methods Manual (TDMM), 14th Edition. Chapter 3, Project Management, Section: Project Closeout. This section lists final test reports as a required deliverable for verification and acceptance of the project.
Keep practicing
Take the free RCDDV14.1 practice test
Ten exam-style questions with answers and explanations, plus the exam facts and study guides.
More questions
Other RCDDV14.1 practice questions
- Question 1A large international manufacturing company is centralizing its IT which is currently spr…
- Question 2Which of the following terms is often used to describe two parallel paths that have ident…
- Question 3An organization initiates an innovation program to deliver exceptional performance and be…
- Question 4The program manager wants to ensure that a program contributes to shareholder value. The …
- Question 5The chief executive officer reminds a program manager that a program must deliver a 30% r…
- Question 6An initiative involves the development of new technology and leverages existing technolog…