RCDDV14.1 practice question 9 of 35

A program manager joins a learn to fix a troubled enterprise-wide customer relationship management (CHM) system Analysis indicates that duplicate…

Full set: 320 questions
A program manager joins a learn to fix a troubled enterprise-wide customer relationship management (CHM) system Analysis indicates that duplicate customer information data is resulting in redundant client information. The program manager accesses the knowledge repository tor similar programs to gather historical data and trends. A corrective action is identified, and a change in process is implemented to regain data integrity What should the program manager do with the knowledge gained from this activity?
Answer options
A: Include the lessons learned in the weekly program report
B: Update the communications management plan
C: Update the lessons learned database Correct answer
D: Communicate the corrective action to the program sponsor
Correct Answer:
C. Update the lessons learned database
Explanation

The activity described is a classic example of organizational learning. The program manager leveraged the existing knowledge repository (lessons learned) to solve a problem and, in doing so, generated new knowledge. The most critical final step in this cycle is to capture this new knowledge and the results of the corrective action. Updating the lessons learned database ensures this information is formally documented and made available for future programs, preventing similar issues and promoting continuous improvement across the organization. This action closes the knowledge management loop.

Why Incorrect

A. This is a transient communication for status updates, not a permanent repository for organizational knowledge.
B. The communications plan dictates how to communicate, not what knowledge is stored; the issue was data integrity, not a communication failure.
D. While the sponsor should be informed, this is a communication task, not the formal process for capturing and archiving lessons learned.

References

1. Project Management Institute. (2017). The Standard for Program Management – Fourth Edition. Section 5.7.3.2, Program Information Management and Reporting, p. 101. (Discusses managing program information, including lessons learned).

2. Project Management Institute. (2017). A Guide to the Project Management Body of Knowledge (PMBOK® Guide) – Sixth Edition. Section 4.4, Manage Project Knowledge, p. 98. (Describes the process of using existing knowledge and creating new knowledge to achieve project objectives and contribute to organizational learning).

3. MIT OpenCourseWare. (2012). 1.040 Project Management, Lecture 22: Project Closeout. (Covers the importance of documenting lessons learned during the project closeout phase for future use). Available: https://ocw.mit.edu/courses/1-040-project-management-spring-2012/