RCDDV14.1 practice question 31 of 35

Alter a company's senior executive management meeting the CEO issues a mandate to automate a new-client on-boarding process that would effectively eliminate the current manual paper-based process. The assigned program sponsor selects a program manager Both the program sponsor and the program manager must ensure that the program charier contains which of the following?

Full set: 320 questions
Answer options
A: Justification, benefits management plan, scope, and resources needed
B: Justification, benefits strategy scope and resource management plan
C: Justification, outcomes, scope, and stakeholder considerations Correct answer
D: Justification, benefits management plan, program business case and stakeholder considerations
Correct Answer:
C. Justification, outcomes, scope, and stakeholder considerations
Explanation

A program charter is a high-level document that formally authorizes the program and links it to the organization's strategic objectives. It defines the program's vision, scope, and expected outcomes. Key components include the program's justification, a high-level scope statement, intended outcomes or benefits, and identification of key stakeholders and their considerations. Detailed plans, such as a benefits management plan or resource management plan, are developed during the Program Definition phase after the charter is approved. The business case is a key input to the charter, not a component within it.

Why Incorrect

A. The benefits management plan and detailed resource needs are developed after the charter is approved, during subsequent program planning activities.
B. A resource management plan is a detailed subsidiary plan created during program planning, not a component of the high-level charter.
D. The program business case is an input used to justify the program and create the charter; the benefits management plan is a detailed output of later planning.

References

Project Management Institute. (2017). The Standard for Program Management (4th ed.). Section 3.3.1 Program Charter, p. 36. "The program charter is the document created and issued by the sponsoring organization that formally authorizes the program... It provides the program manager with the authority to apply organizational resources to program activities."

Project Management Institute. (2017). The Standard for Program Management (4th ed.). Figure 3-4, Inputs, Tools & Techniques, and Outputs of the Develop Program Charter Process, p. 37. (Shows Business Case as an input).