RCDDV14.1 practice question 32 of 35

Which of the following serves as a guiding principle for a program manager when preparing a program work breakdown structure?

Full set: 320 questions
Answer options
A: Decompose the program work based upon available resources
B: Decompose the program to the work package level
C: Decompose the program lo the architecture baseline level
D: Decompose the program at a level sufficient to achieve control Correct answer
Correct Answer:
D. Decompose the program at a level sufficient to achieve control
Explanation

The Program Work Breakdown Structure (PWBS) is a hierarchical decomposition of the total scope of work to be carried out by the program team. The primary guiding principle for its creation is to break down the work to a level that is sufficient for effective planning, execution, monitoring, and control. This level of detail, often called a control account, allows the program manager to accurately estimate costs and durations, assign responsibilities, and measure performance. Decomposing too far is inefficient, while not decomposing enough leads to a loss of control.

Why Incorrect

A. Decompose the program work based upon available resources: The WBS defines the work; resource allocation happens later. The work scope should not be defined by who is available.
B. Decompose the program to the work package level: The work package is the lowest level in a project WBS. A program WBS may not need to be decomposed to this level of detail.
C. Decompose the program lo the architecture baseline level: The architecture baseline is a technical artifact; the WBS is a scope management tool. They are related but not the same decomposition principle.

References

1. BICSI, Telecommunications Distribution Methods Manual (TDMM), 14th ed., Chapter 3, Project Management, Section: Creating the Work Breakdown Structure (WBS). The manual emphasizes that the WBS decomposes the project scope into manageable components, which is the essence of achieving control.

2. Project Management Institute (PMI), The Standard for Program Management – Fourth Edition. Section 4.3.2, "Program Work Breakdown Structure." This section states the PWBS is decomposed to a level of detail that supports the management of the program work.