A representative of the customer has asked the Development Team to add a very important item to an ongoing Sprint. What should they do?
Full set: 148 questionsDomain Implement Phase
The Product Owner is solely responsible for managing the Product Backlog, which includes its content, availability, and ordering. The Development Team works on the items selected for the Sprint Backlog. If any stakeholder, including a customer representative, wants to add or change work in a Sprint, they must discuss it with the Product Owner. The Product Owner will then assess the request's priority and impact and negotiate with the Development Team if a change to the current Sprint is necessary. The Development Team should not take direction from other sources.
A: The Scrum Master facilitates the process but does not manage the product's content or priority; that is the Product Owner's role. B: Accepting the item, even if formally requested, bypasses the Product Owner's authority and disrupts the planned Sprint Goal. D: Simply refusing is not collaborative. The correct action is to redirect the representative to the person responsible for the backlog, the Product Owner.
1. A Guide to the Scrum Body of Knowledge (SBOK® Guide), 4th Edition, SCRUMstudy. Chapter 3, Section 3.5.1, Role of the Product Owner. "The Product Owner is the voice of the customer... and is responsible for ensuring that the Scrum Team delivers value. The Product Owner is responsible for the Product Backlog and for prioritizing the items in it."
2. Schwaber, K., & Sutherland, J. (2020). The Scrum Guide. Scrum.org. p. 5. "The Product Owner is responsible for maximizing the value of the product resulting from work of the Development Team... No one can force the Development Team to work from a different set of requirements."
Keep practicing
Take the free SMC practice test
Ten exam-style questions with answers and explanations, plus the exam facts and study guides.
More questions
Other SMC practice questions
- Question 1Which of the following about User Story Acceptance Criteria is true?
- Question 2You are the Scrum Master for your organization and you are working to create a Developmen…
- Question 3Impediments are a part of any project. Which of the following is NOT true about impedimen…
- Question 4The Scrum Master is attending a meeting in which the Scrum Team is estimating the effort …
- Question 5To enable collaboration, the Product Owner, the Scrum Master, and the Scrum Team collabor…
- Question 6George is a Scrum Master on a project to develop a Course Management System and Leave Man…