SMC practice question 17 of 25
During the Form Scrum Team process, the Scrum Master must collaborate with the Product Owner to enable him or her to select the team members. Which of following sets of Traits is desirable of a Scrum Team member?
Full set: 148 questionsDomain Scrum Roles
A desirable Scrum Team is cross-functional, collaborative, and possesses the necessary business domain knowledge to deliver value. "Cross-functional outlook" means team members have varied skills to complete the work without depending on outsiders. "Collaborative" nature is essential for the team to work together effectively. "Business Domain knowledge" enables the team to understand user requirements and make informed decisions. This combination ensures the team is self-sufficient and aligned with the project's business goals, as outlined in the Scrum framework.
A. Not every team member is expected to be a "Scrum Expert"; that is primarily the Scrum Master's role.
B. While "Negotiation skills" are useful, a "Cross-functional outlook" is a more fundamental and defining characteristic of a Scrum Team.
D. The term "Independent" is misleading; Scrum emphasizes interdependence and collaboration within the team, not individual independence.
SCRUMstudy, A Guide to the Scrum Body of Knowledge (SBOK® Guide), 3rd ed. (Phoenix: SCRUMstudy, 2017), 41. Section 3.4 describes the Scrum Team as cross-functional and self-organizing, which requires a collaborative and cross-functional outlook.
SCRUMstudy, A Guide to the Scrum Body of Knowledge (SBOK® Guide), 3rd ed. (Phoenix: SCRUMstudy, 2017), 44. Section 3.5.2 discusses Team Selection Criteria, which would prioritize collaborative and cross-functional members with relevant domain knowledge.
Keep practicing
Take the free SMC practice test
Ten exam-style questions with answers and explanations, plus the exam facts and study guides.
More questions
Other SMC practice questions
- Question 1Which of the following about User Story Acceptance Criteria is true?
- Question 2You are the Scrum Master for your organization and you are working to create a Developmen…
- Question 3Impediments are a part of any project. Which of the following is NOT true about impedimen…
- Question 4The Scrum Master is attending a meeting in which the Scrum Team is estimating the effort …
- Question 5To enable collaboration, the Product Owner, the Scrum Master, and the Scrum Team collabor…
- Question 6George is a Scrum Master on a project to develop a Course Management System and Leave Man…