SMC practice question 16 of 25
As a Scrum Master, it is important that you assess skill gaps and training requirements for the team members, and map the skills, capabilities, and interest level of team members in using those skills and capabilities on a project. Which one of the following tools can help you do this?
Full set: 148 questionsDomain Initiate Phase
The Organizational Resource Matrix is a tool used in human resource planning to map the required skills for a project against the available personnel and their existing skill sets. As a Scrum Master, this tool is invaluable for identifying skill gaps, assessing training needs, and ensuring the team has the necessary competencies. It provides a clear visual representation of the team's capabilities, interests, and areas for development, facilitating the formation of a cross-functional and effective Scrum Team.
A. Skills Requirement Matrix: This is a generic term. The specific tool mentioned in the ScrumStudy Body of Knowledge (SBOK® Guide) for this purpose is the Organizational Resource Matrix.
B. Organizational Deployment Method: This is not a recognized tool for assessing team skills; it relates more to deploying resources or products across an organization.
C. Daily Standup: This is a Scrum event for daily planning and synchronization, not a tool for a comprehensive assessment of skill gaps and training requirements.
1. A Guide to the Scrum Body of Knowledge (SBOK® Guide), 3rd Edition. SCRUMstudy, VMEdu, Inc., 2017. Section 4.4.2.3, "Tools for Form Scrum Team," p. 81.
Keep practicing
Take the free SMC practice test
Ten exam-style questions with answers and explanations, plus the exam facts and study guides.
More questions
Other SMC practice questions
- Question 1Which of the following about User Story Acceptance Criteria is true?
- Question 2You are the Scrum Master for your organization and you are working to create a Developmen…
- Question 3Impediments are a part of any project. Which of the following is NOT true about impedimen…
- Question 4The Scrum Master is attending a meeting in which the Scrum Team is estimating the effort …
- Question 5To enable collaboration, the Product Owner, the Scrum Master, and the Scrum Team collabor…
- Question 6George is a Scrum Master on a project to develop a Course Management System and Leave Man…