SMC practice question 15 of 25

Each Scrum role has specific responsibilities in managing a Scrum project. Below, choose the role that is correctly matched to its responsibility.

Full set: 148 questions

Domain Initiate Phase

Answer options
A: Product Owner - invites to a grooming session only those stakeholders whose feedback is required and who can make final decisions about which suggested changes can be considered as Formal Change Requests. Correct answer
B: Scrum Master - ensures that the requirements and Acceptance Criteria are not altered during the Sprint Review Meeting.
C: Stakeholders - incorporate new and modified features into the deliverables whenever possible.
D: Scrum Team - decide whether the change can wait until the next Sprint or represents an urgent situation that may require ending the current Sprint and starting a new one.
Correct Answer:
A. Product Owner - invites to a grooming session only those stakeholders whose feedback is required and who can make final decisions about which suggested changes can be considered as Formal Change Requests.
Explanation

The Product Owner is responsible for maximizing the value of the product and managing stakeholder expectations. This includes facilitating Product Backlog Refinement (Grooming) sessions. The PO strategically invites relevant stakeholders to these meetings to gather essential feedback and clarify requirements. Within the ScrumStudy framework, which accommodates formal change control, the PO also manages decisions on which suggested changes become Formal Change Requests, ensuring alignment with project goals and value.

Why Incorrect

B. The Scrum Master facilitates the Sprint Review, but the Product Owner owns the requirements; feedback during this meeting can and often does lead to changes in the Product Backlog.
C. The Scrum Team (specifically, the developers) is responsible for incorporating features into the deliverables, not the Stakeholders, who provide input and feedback.
D. Only the Product Owner has the authority to cancel a Sprint. This decision is not made by the entire Scrum Team, though their input is valuable.

References

- A Guide to the Scrum Body of Knowledge (SBOK® Guide), 3rd Edition. (2017). ScrumStudy. Section 3.4.1, p. 43 (Product Owner's Responsibilities).

- A Guide to the Scrum Body of Knowledge (SBOK® Guide), 3rd Edition. (2017). ScrumStudy. Section 8.3.2, p. 152 (Grooming the Prioritized Product Backlog).

- A Guide to the Scrum Body of Knowledge (SBOK® Guide), 3rd Edition. (2017). ScrumStudy. Section 7.6, p. 132 (Control).