SMC practice question 14 of 25

The Chief Scrum Master is a part of the Scrum Core Team that assembles to retrospect the project and to identify, document, and internalize the lessons learned. There are various tools to Retrospect Project during the Retrospect Project Meeting. Which of the following tools can be used in this process?

Full set: 148 questions

Domain Review and Retrospect Phase

Answer options
A: Gap analysis. Correct answer
B: SWOT analysis. Correct answer
C: Proof of Concept.
D: Speed Boat. Correct answer
Correct Answer:
A. Gap analysis.; B. SWOT analysis.; D. Speed Boat.
Explanation

The Retrospect Project Meeting is conducted to determine lessons learned that could be applied to future projects. SWOT analysis is used to assess the project's strengths, weaknesses, opportunities, and threats. Gap analysis helps compare the planned or expected results with the actual results to identify shortfalls. Speed Boat is a collaborative technique where the team identifies factors that helped the project move forward (wind in the sails) and factors that hindered it (anchors). These tools facilitate a comprehensive review of the completed project.

Why Incorrect

C. Proof of Concept: This is used to verify the feasibility of a technical idea or feature during development, not as a tool for a project retrospective.

References

SCRUMstudy. (2017). A Guide to the Scrum Body of Knowledge (SBOK® Guide) (3rd ed.). Section 6.4.2.2, Tools for Retrospect Project, pp. 150-151.