A company that builds propellers for ships has incurred heavy losses while implementing the product at the end of the project. This is because a…
Full set: 148 questionsDomain Agile and Scrum Overview
The scenario describes a failure to adapt to changing customer requirements, a classic problem in traditional waterfall projects. Scrum addresses this through iterative development. By building the product in short cycles (Sprints), the team can regularly present working increments to the customer. This creates frequent opportunities for feedback and allows for changes to be incorporated in subsequent Sprints. This ensures the final product aligns with the current business needs, rather than outdated requirements, thus avoiding the losses described.
A. Value-based prioritization is about ordering work, not the mechanism for incorporating changes throughout the development lifecycle.
B. Appropriation is not a standard Scrum aspect; it generally refers to adapting Scrum, which is too broad and not the specific principle at play here.
D. Transparency makes issues and changes visible, but it is the iterative process that provides the framework to act on them effectively.
1. A Guide to the Scrum Body of Knowledge (SBOK® Guide), 3rd Edition. (2017). SCRUMstudy, a brand of VMEdu, Inc. Section 2.4, "Iterative Development," p. 30. The guide states, "The iterative model is more flexible in ensuring that any change requested by the customer can be included as part of the project."
2. A Guide to the Scrum Body of Knowledge (SBOK® Guide), 3rd Edition. (2017). SCRUMstudy, a brand of VMEdu, Inc. Section 1.4.2, "Scrum vs. Traditional Project Management," p. 12. This section contrasts how Scrum's iterative nature handles change compared to traditional models.
Keep practicing
Take the free SMC practice test
Ten exam-style questions with answers and explanations, plus the exam facts and study guides.
More questions
Other SMC practice questions
- Question 1Which of the following about User Story Acceptance Criteria is true?
- Question 2You are the Scrum Master for your organization and you are working to create a Developmen…
- Question 3Impediments are a part of any project. Which of the following is NOT true about impedimen…
- Question 4The Scrum Master is attending a meeting in which the Scrum Team is estimating the effort …
- Question 5To enable collaboration, the Product Owner, the Scrum Master, and the Scrum Team collabor…
- Question 6George is a Scrum Master on a project to develop a Course Management System and Leave Man…