SMC practice question 13 of 25
A company that builds propellers for ships has incurred heavy losses while implementing the product at the end of the project. This is because a…
Choose your answer, then check it against the explanation.
Domain Agile and Scrum Overview
A company that builds propellers for ships has incurred heavy losses while implementing the product
at the end of the project. This is because a large number of customer requirements which changed
during the project were not incorporated into the deliverables. The company could have avoided this
situation if it had applied the Scrum Methodology, as it would have ensured that any change
requested by the customer was included as part of the project, and that the team produced
deliverables that were better suited to the final business environment. Which Scrum aspect is being
emphasized here?
Question 13 of 25
Keep practicing
Take the free SMC practice test
Ten exam-style questions with answers and explanations, plus the exam facts and study guides.
More questions
Other SMC practice questions
- Question 1Which of the following about User Story Acceptance Criteria is true?
- Question 2You are the Scrum Master for your organization and you are working to create a Developmen…
- Question 3Impediments are a part of any project. Which of the following is NOT true about impedimen…
- Question 4The Scrum Master is attending a meeting in which the Scrum Team is estimating the effort …
- Question 5To enable collaboration, the Product Owner, the Scrum Master, and the Scrum Team collabor…
- Question 6George is a Scrum Master on a project to develop a Course Management System and Leave Man…