SMC practice question 12 of 25

Lynn is the Scrum Master for her organization and she's working with seven Development Teams on a single Scrum project. What statement best describes the starting date for these seven Development Teams?

Full set: 148 questions

Domain Agile and Scrum Overview

Answer options
A: All Development Teams should start their Sprints on the same day. Correct answer
B: Each Development Team should start their Sprint by staggering their start date by one week.
C: All Development Teams must select their sprint duration by the assigned project start date.
D: Each Development Team will participate in Sprint Planning to determine which Development Team should start in a specific order.
Correct Answer:
A. All Development Teams should start their Sprints on the same day.
Explanation

When multiple Development Teams work on a single product, it is a best practice to synchronize their Sprints. This means all teams should start and end their Sprints on the same day and typically use the same Sprint length. This aligned cadence, or rhythm, is crucial for managing dependencies between teams. It greatly simplifies the process of creating a single, integrated, and potentially shippable increment at the end of each Sprint. It also facilitates scaled events like a combined Sprint Review and coordinated Sprint Planning.

Why Incorrect

B. Staggering Sprint start dates would create significant integration challenges and make it nearly impossible to produce a single integrated increment at a predictable point.
C. Sprint duration is important, but this option incorrectly links it to the "assigned project start date" and doesn't address the coordination of start dates between teams.
D. Sprint Planning is for planning the work for the upcoming Sprint, not for deciding the order in which teams should start their Sprints.

References

1. A Guide to the Scrum Body of Knowledge (SBOK® Guide), 3rd Edition. (2017). SCRUMstudy, a brand of VMEdu, Inc. Section 14.4, "Conduct Sprints," p. 348. The guide explicitly recommends, "It is recommended that all teams have the same Sprint start and end dates, and the same Sprint length."

2. A Guide to the Scrum Body of Knowledge (SBOK® Guide), 3rd Edition. (2017). SCRUMstudy, a brand of VMEdu, Inc. Section 14.2.1, "Chief Product Owner," p. 342. This section discusses coordination across teams, which is enabled by practices like synchronized Sprints.