SMC practice question 8 of 25
A Scrum Team must produce the following artifacts. Select all that apply.
Full set: 148 questionsDomain Scrum Roles
The Scrum framework defines three official artifacts that are essential for transparency and for inspecting progress. These are the Product Backlog, the Sprint Backlog, and the Increment. The Product Backlog is the ordered list of everything known to be needed in the product. The Sprint Backlog is the set of Product Backlog items selected for the Sprint, plus a plan for delivering the Increment. The Increment is the sum of all the Product Backlog items completed during a Sprint and the value of the increments of all previous Sprints.
B. A Project Plan is a traditional project management document; Scrum uses the emergent Product and Sprint Backlogs for planning.
C. Test Case Specifications are detailed work products, not a formal, high-level Scrum artifact.
D. A Design Document is a potential output of the Development Team's work, but it is not a required Scrum artifact.
E. A Project Status Report is replaced in Scrum by the transparency provided by the artifacts and daily events.
1. SCRUMstudy. (2017). A Guide to the Scrum Body of Knowledge (SBOK® Guide) (3rd ed.). Chapter 7, Scrum Artifacts. This chapter explicitly defines the Product Backlog, Sprint Backlog, and Product Increment as the key artifacts.
2. Schwaber, K., & Sutherland, J. (2020). The Scrum Guide. Scrum.org. p. 12. "Scrum’s artifacts represent work or value. They are designed to maximize transparency of key information... The artifacts are Product Backlog, Sprint Backlog, and Increment."
Keep practicing
Take the free SMC practice test
Ten exam-style questions with answers and explanations, plus the exam facts and study guides.
More questions
Other SMC practice questions
- Question 1Which of the following about User Story Acceptance Criteria is true?
- Question 2You are the Scrum Master for your organization and you are working to create a Developmen…
- Question 3Impediments are a part of any project. Which of the following is NOT true about impedimen…
- Question 4The Scrum Master is attending a meeting in which the Scrum Team is estimating the effort …
- Question 5To enable collaboration, the Product Owner, the Scrum Master, and the Scrum Team collabor…
- Question 6George is a Scrum Master on a project to develop a Course Management System and Leave Man…
