SMC practice question 8 of 25

A Scrum Team must produce the following artifacts. Select all that apply.

Full set: 148 questions

Domain Scrum Roles

Answer options
A: Increment Correct answer
B: Project Plan
C: Test Case Specifications
D: Design Document
E: Project Status Report
F: Sprint Backlog Correct answer
G: Product Backlog Correct answer
Correct Answer:
A. Increment; F. Sprint Backlog; G. Product Backlog
Explanation

The Scrum framework defines three official artifacts that are essential for transparency and for inspecting progress. These are the Product Backlog, the Sprint Backlog, and the Increment. The Product Backlog is the ordered list of everything known to be needed in the product. The Sprint Backlog is the set of Product Backlog items selected for the Sprint, plus a plan for delivering the Increment. The Increment is the sum of all the Product Backlog items completed during a Sprint and the value of the increments of all previous Sprints.

Why Incorrect

B. A Project Plan is a traditional project management document; Scrum uses the emergent Product and Sprint Backlogs for planning.
C. Test Case Specifications are detailed work products, not a formal, high-level Scrum artifact.
D. A Design Document is a potential output of the Development Team's work, but it is not a required Scrum artifact.
E. A Project Status Report is replaced in Scrum by the transparency provided by the artifacts and daily events.

References

1. SCRUMstudy. (2017). A Guide to the Scrum Body of Knowledge (SBOK® Guide) (3rd ed.). Chapter 7, Scrum Artifacts. This chapter explicitly defines the Product Backlog, Sprint Backlog, and Product Increment as the key artifacts.

2. Schwaber, K., & Sutherland, J. (2020). The Scrum Guide. Scrum.org. p. 12. "Scrum’s artifacts represent work or value. They are designed to maximize transparency of key information... The artifacts are Product Backlog, Sprint Backlog, and Increment."