Andy, a Scrum Master, is helping his team draft a Sprint Backlog. In which of the following phases would this Scrum process be in?

Full set: 148 questions

Domain Implement Phase

Answer options
A: Initiate
B: Plan and Estimate Correct answer
C: Implement
D: Review and Retrospect
Correct Answer:
B. Plan and Estimate
Explanation

The Scrum framework, as defined by ScrumStudy, is organized into phases and processes. The creation of the Sprint Backlog occurs during the Sprint Planning Meeting. This meeting is a key process within the "Plan and Estimate" phase. In this phase, the Scrum Team, facilitated by the Scrum Master, selects User Stories from the Prioritized Product Backlog and breaks them down into tasks to form the Sprint Backlog for the upcoming Sprint. This phase follows the "Initiate" phase and precedes the "Implement" phase.

Why Incorrect

A. The Initiate phase focuses on creating the Project Vision, identifying the Scrum Master and Product Owner, and developing the initial Prioritized Product Backlog, not the Sprint Backlog.
C. The Implement phase is where the Development Team works on the tasks defined in the Sprint Backlog to create the Sprint's deliverable. The Sprint Backlog is an input to this phase.
D. The Review and Retrospect phase occurs after the Sprint is completed. It includes the Sprint Review and Retrospect Sprint meetings to inspect the increment and the process.

References

ScrumStudy. (2017). A Guide to the Scrum Body of Knowledge (SBOK® Guide) (3rd ed.). Section 4.3, Create Sprint Backlog, p. 155. The guide explicitly places the "Create Sprint Backlog" process within the "Plan and Estimate" phase.

ScrumStudy. (2017). A Guide to the Scrum Body of Knowledge (SBOK® Guide) (3rd ed.). Figure 3-3, Scrum Flow, p. 32. This diagram visually maps the "Create Sprint Backlog" process to the "Plan and Estimate" phase.