A customer migrates from a traditional Layer 2 data center network into a new SDN-based. spine- and-leaf VXLAN EVPN data center within the same location. The networks are joined to enable host migration at Layer 2 Which activity should be completed each time a legacy network is migrated?
Full set: 397 questionsDuring a phased migration from a traditional Layer 2 network to a VXLAN EVPN fabric, a Layer 2 interconnect (trunk) is established to extend VLANs between the two environments. This allows for the seamless migration of hosts. Once all hosts belonging to a specific VLAN have been moved to the new VXLAN fabric, the Layer 2 extension for that VLAN is no longer required. The final step for that migrated network is to prune the corresponding VLAN from the interconnect trunks. This is a crucial housekeeping activity to prevent potential broadcast storms, avoid suboptimal traffic paths (tromboning), and decommission the legacy network segment cleanly.
B. The migrated network should have a VXLAN VNID configured within the new network. This is a prerequisite step performed before migration begins, not an activity completed after a network is migrated.
C. The migrated network should be advertised to the EVPN network as a Type 2 network. This is an automatic function of the EVPN control plane that occurs as hosts are learned; it is not a manual post-migration task.
D. The migrated network should be added to the EVPN BGP routing. This refers to the initial configuration of the VLAN-to-VNI mapping within the BGP EVPN address family, which must be done to enable the migration.
1. Cisco Press
Building Data Centers with VXLAN BGP EVPN: A Cisco NX-OS Perspective
Reference: Chapter 11
"Migration Strategies
" Section "Workload Migration Phase."
Content: The book details the migration process in phases. After workloads for a given VLAN are moved
the final step is the "Decommissioning Phase
" which involves removing the VLAN and its associated SVI from the legacy network and the interconnects. Pruning the VLAN from the trunk is a key part of this decommissioning.
2. Cisco Live Presentation
BRKDCN-2433 - Data Center Migration Strategies
Reference: Slide deck section on "Migration Execution" and "Post-Migration Cleanup."
Content: The presentation outlines a structured migration methodology: Prepare
Migrate
and Decommission. The "Decommission" phase explicitly includes steps such as removing the VLAN from the trunk ports connecting the legacy and new fabrics once the migration for that VLAN is complete and verified. This prevents residual L2 paths and cleans up the configuration.
3. Cisco
VXLAN EVPN Multi-Site Design and Deployment Guide
Reference: Section "Interconnecting VXLAN EVPN with Traditional L2 Networks."
Content: While discussing the interconnectivity for migration
the guide emphasizes the importance of proper VLAN management on the border leaf switches. The logical conclusion of migrating a VLAN off the legacy network is to remove its configuration from the interconnect to finalize the transition and enforce the new traffic patterns through the VXLAN fabric.
Keep practicing
Take the free 400-007 practice test
Ten exam-style questions with answers and explanations, plus the exam facts and study guides.
More questions
Other 400-007 practice questions
- Question 1An engineer must design a network for a company that uses OSPF LFA to reduce loops. Which…
- Question 2Your company wants to deploy a new data center infrastructure Based on the requirements y…
- Question 3You have been tasked with designing a data center interconnect as part of business contin…
- Question 4A service provider hires you to design its new managed CE offering to meet these requirem…
- Question 5Which three Cisco products are used in conjunction with Red Hat to provide an NFVi soluti…
- Question 6You were tasked to enhance the security of a network with these characteristics: • A pool…