AACE-INTERNATIONAL-PSP practice question 4 of 30
By subtracting a measured unit productivity rate during an impacted period from the unit productivity rate during an unimpacted period, the resulting value represents:
Full set: 211 questionsThis calculation is the basis of the "measured mile" analysis, a widely accepted method for quantifying lost productivity. It compares the productivity rate during an unimpacted period (the "measured mile" or baseline) against the rate achieved during an impacted period. The difference between these two rates represents the quantifiable loss in labor productivity caused by the impacts or disruptions. This value is crucial for substantiating claims for additional costs due to inefficiency.
A. Acceleration: This is the act of completing work faster than planned, not a calculation of lost efficiency.
B. Production output: This is the physical quantity of work completed (e.g., cubic yards of concrete), not a rate difference.
D. Productivity efficiency: This is typically a ratio, such as the earned value divided by the actual cost (Cost Performance Index), not a subtraction of rates.
1. AACE International
Recommended Practice No. 25R-03
"Estimating Lost Labor Productivity in Construction Claims
" (June 28
2004)
Section 4.2
p. 8. This section describes the measured mile approach
which is founded on comparing productivity in an unimpacted period to an impacted period to determine the loss.
2. Zayed
T. M.
& Halpin
D. W. (2004). Productivity and cost regression models for pile construction. Journal of Construction Engineering and Management
130(6)
779-789. https://doi.org/10.1061/(ASCE)0733-9364(2004)130:6(779). The paper discusses methods of measuring productivity
where loss is the deviation from an established norm or baseline rate.
Keep practicing
Take the free AACE-INTERNATIONAL-PSP practice test
Ten exam-style questions with answers and explanations, plus the exam facts and study guides.
More questions
Other AACE-INTERNATIONAL-PSP practice questions
- Question 5Using the normal schedule, given Activity 3001 and the relationship with Activity 4001. w…
- Question 8How many workdays occur from the start of the Product Testing to the Product Available mi…
- Question 9In order for a claimant to be entitled to an extension of contract time for a delay event…
- Question 11The addition of which of the following relationships would cause a logic loop?
- Question 12Which of the following options is NOT a feasible method to reduce the overall completion …
- Question 14At a minimum, periodic reporting must be done at what interval?