AACE-INTERNATIONAL-PSP practice question 11 of 30
The addition of which of the following relationships would cause a logic loop?
Full set: 211 questionsA logic loop (circular dependency) occurs when an activity is made both a successor and a predecessor of itself through a chain of relationships, preventing forward or backward pass calculation. In the given network, activity F is already a predecessor of I; adding the opposite link “F-I” makes I simultaneously precede and follow F, completing a closed cycle. The network solver will flag this as “circular logic” and halt. None of the other listed relationships close an existing predecessor–successor chain, so they leave the logic acyclic.
A. O H-D adds a normal finish-to-start tie that does not feed back into H or O.
B. O C-J links two nodes that had no reciprocal ties, so no cycle forms.
D. O I-C also connects independent nodes without completing a predecessor → successor → predecessor loop.
1. AACE International Recommended Practice 49R-06
“Identifying the Critical Path
” §4.1
Circular Logic
pp. 5-6.
2. AACE International
Skills and Knowledge of Cost Engineering
6th ed.
Ch. 19
“Scheduling
” p. 379 (discussion of prohibited circular logic).
3. Stanford Univ. CEE-159/259 “Construction Planning & Control
” Lecture 7 notes
p. 4
“Circular relationships will cause CPM calculation failure.”
Keep practicing
Take the free AACE-INTERNATIONAL-PSP practice test
Ten exam-style questions with answers and explanations, plus the exam facts and study guides.
More questions
Other AACE-INTERNATIONAL-PSP practice questions
- Question 4By subtracting a measured unit productivity rate during an impacted period from the unit …
- Question 5Using the normal schedule, given Activity 3001 and the relationship with Activity 4001. w…
- Question 8How many workdays occur from the start of the Product Testing to the Product Available mi…
- Question 9In order for a claimant to be entitled to an extension of contract time for a delay event…
- Question 12Which of the following options is NOT a feasible method to reduce the overall completion …
- Question 14At a minimum, periodic reporting must be done at what interval?