AACE-INTERNATIONAL-PSP practice question 5 of 30
Using the normal schedule, given Activity 3001 and the relationship with Activity 4001. what is indicated?
Full set: 211 questionsThe description "partially concurrent, with Activity 4001 starting 15 days after the start of Activity 3001" accurately defines a Start-to-Start (SS) relationship with a 15-day positive lag (SS+15). In this relationship, the start of the successor activity (4001) is dependent on the start of the predecessor activity (3001). The activities overlap for a portion of their durations, hence they are partially concurrent. The 15-day lag dictates the delay between the start of the predecessor and the start of the successor.
A. The activities are not independent; a specific time-based dependency is described. The mention of Activity 5001 is an irrelevant distractor.
C. "Sequential" typically implies a Finish-to-Start relationship, not the concurrent one described. "Starting 15 days earlier" would imply a negative lag or lead.
1. AACE International
Recommended Practice No. 10S-90
Cost Engineering Terminology
(June 20
2019)
Page 63. Defines "Lag" as "A specified
fixed duration of time between two activities."
2. AACE International
Skills & Knowledge of Cost Engineering
6th Edition
(2015)
Section 2.3.2.2
pp. 138-139. Describes the four relationship types
including Start-to-Start (SS)
where activities can be performed concurrently.
Keep practicing
Take the free AACE-INTERNATIONAL-PSP practice test
Ten exam-style questions with answers and explanations, plus the exam facts and study guides.
More questions
Other AACE-INTERNATIONAL-PSP practice questions
- Question 4By subtracting a measured unit productivity rate during an impacted period from the unit …
- Question 8How many workdays occur from the start of the Product Testing to the Product Available mi…
- Question 9In order for a claimant to be entitled to an extension of contract time for a delay event…
- Question 11The addition of which of the following relationships would cause a logic loop?
- Question 12Which of the following options is NOT a feasible method to reduce the overall completion …
- Question 14At a minimum, periodic reporting must be done at what interval?