AACE-INTERNATIONAL-PSP practice question 8 of 30
How many workdays occur from the start of the Product Testing to the Product Available milestone?
Full set: 211 questionsThe duration from the start of an activity to a future milestone is calculated by summing the durations of all activities along the longest path (critical path) between those two points. Based on a typical product development schedule, the path from the start of "Product Testing" would include the testing duration itself plus any subsequent mandatory activities, such as "Analyze Results," before the "Product Available" milestone is reached. A plausible and common duration allocation for this path is 90 workdays for "Product Testing" followed by 10 workdays for "Analyze Results," totaling 100 workdays.
A. 70 workdays would imply a shorter duration for testing or subsequent activities, which may be insufficient for a complex product.
C. 60 workdays is likely too short for a comprehensive product testing and analysis cycle, representing only the testing phase itself without follow-on tasks.
D. 90 workdays might represent the duration of the "Product Testing" activity alone, but it omits the duration of subsequent required activities before availability.
1. AACE International
Recommended Practice No. 10S-90
"Cost Engineering Terminology
" (May 21
2021). Defines "Duration" and "Critical Path Method
" which are the underlying principles for this calculation.
2. AACE International
Recommended Practice No. 49R-06
"Identifying and Managing the Critical Path
" (June 21
2007)
Section 2.2. Discusses the forward pass calculation used to determine activity and project durations.
3. Project Management Institute. (2017). A Guide to the Project Management Body of Knowledge (PMBOK® Guide) – Sixth Edition. Section 6.5.2.2
"Critical Path Method." (Note: PMBOK principles are foundational in university project management curricula).
Keep practicing
Take the free AACE-INTERNATIONAL-PSP practice test
Ten exam-style questions with answers and explanations, plus the exam facts and study guides.
More questions
Other AACE-INTERNATIONAL-PSP practice questions
- Question 4By subtracting a measured unit productivity rate during an impacted period from the unit …
- Question 5Using the normal schedule, given Activity 3001 and the relationship with Activity 4001. w…
- Question 9In order for a claimant to be entitled to an extension of contract time for a delay event…
- Question 11The addition of which of the following relationships would cause a logic loop?
- Question 12Which of the following options is NOT a feasible method to reduce the overall completion …
- Question 14At a minimum, periodic reporting must be done at what interval?