AACE-INTERNATIONAL-PSP practice question 12 of 30
Which of the following options is NOT a feasible method to reduce the overall completion time of the toll road program?
Full set: 211 questionsFeasible methods to reduce project duration involve schedule compression techniques like crashing (adding resources) or fast-tracking. Subcontracting work (A), reallocating internal forces (B), and re-phasing the project (D) are all valid schedule compression strategies. However, proceeding with work before mandatory environmental studies are complete (C) is typically illegal and a violation of regulatory requirements. Such an action would introduce unacceptable risk, including fines and stop-work orders, and is therefore not a professionally or legally feasible method for project acceleration.
A. Subcontracting is a form of crashing the schedule by adding external resources to perform work in parallel or faster.
B. Allocating forces from other contracts is a valid method of adding resources (crashing) to critical path activities.
D. Reducing the number of phases is a form of fast-tracking or re-sequencing the overall program logic to achieve earlier completion.
1. AACE International
Recommended Practice No. 49R-06
"Identifying and Analyzing Constructive Acceleration
" (October 25
2007)
Section 2.3
"Methods of Acceleration." This RP discusses legitimate methods such as overtime
adding labor/equipment
and resequencing. It does not include violating legal prerequisites.
2. Hollmann
J. K. (Ed.). (2015). AACE International's Skills & Knowledge of Cost Engineering (6th ed.). Section 2.4.7
"Schedule Development
" p. 2.4.7-5. Discusses schedule compression techniques like crashing and fast-tracking.
Keep practicing
Take the free AACE-INTERNATIONAL-PSP practice test
Ten exam-style questions with answers and explanations, plus the exam facts and study guides.
More questions
Other AACE-INTERNATIONAL-PSP practice questions
- Question 4By subtracting a measured unit productivity rate during an impacted period from the unit …
- Question 5Using the normal schedule, given Activity 3001 and the relationship with Activity 4001. w…
- Question 8How many workdays occur from the start of the Product Testing to the Product Available mi…
- Question 9In order for a claimant to be entitled to an extension of contract time for a delay event…
- Question 11The addition of which of the following relationships would cause a logic loop?
- Question 14At a minimum, periodic reporting must be done at what interval?