AACE-INTERNATIONAL-PSP practice question 9 of 30
In order for a claimant to be entitled to an extension of contract time for a delay event (and further to be considered compensable):
Full set: 211 questionsFor a delay to warrant an extension of the contract completion date, it must delay the project's overall completion. In Critical Path Method (CPM) scheduling, the project completion date is determined by the longest path of activities, known as the critical path. Therefore, a delay event must impact an activity on the critical path (or consume float such that a new critical path is formed) to justify a time extension. A delay to a non-critical activity that does not exhaust its float will not delay project completion.
B. The delay must be concurrent with the delay attributable to both parties: Concurrency is a specific delay scenario, not a general prerequisite for entitlement to a time extension.
C. The delay must not cause monetary harm to the defendant: A compensable delay explicitly involves the defendant (owner) providing monetary compensation for harm suffered by the claimant (contractor).
D. The delay must affect the contractor's planned construction schedule: This is too vague; a delay can affect a non-critical part of the schedule without impacting the final completion date.
1. AACE International Recommended Practice No. 29R-03
"Forensic Schedule Analysis
" (April 25
2011). Section 4.1.A states
"The basic premise of all CPM-based schedule analysis methods is that a party is entitled to a time extension only to the extent that a delay to a critical path activity is caused by the other party."
2. AACE International
Skills and Knowledge of Cost Engineering
6th Ed.
Morgantown
WV: AACE International
2015. Chapter 25 (Project Scheduling) explains that only delays to critical path activities will delay the project completion date.
3. Stephenson
H. L. (Ed.). (2019). AACE International's Planning & Scheduling Professional (PSP) Certification Study Guide
3rd Ed. AACE International. The guide repeatedly emphasizes that impact to the critical path is the basis for granting a time extension in a delay claim.
Keep practicing
Take the free AACE-INTERNATIONAL-PSP practice test
Ten exam-style questions with answers and explanations, plus the exam facts and study guides.
More questions
Other AACE-INTERNATIONAL-PSP practice questions
- Question 4By subtracting a measured unit productivity rate during an impacted period from the unit …
- Question 5Using the normal schedule, given Activity 3001 and the relationship with Activity 4001. w…
- Question 8How many workdays occur from the start of the Product Testing to the Product Available mi…
- Question 11The addition of which of the following relationships would cause a logic loop?
- Question 12Which of the following options is NOT a feasible method to reduce the overall completion …
- Question 14At a minimum, periodic reporting must be done at what interval?