PFMP practice question 17 of 35
A big strategic change occurred at the organization level and has impacted multiple portfolios in the organization including yours. The sponsor has asked you to analyze the change and update the needed documents. You managed this change and are currently updating the Portfolio Management Plan. Which of the following are part of this update
Full set: 490 questionsA significant strategic change at the organizational level has a cascading effect on a portfolio. The Portfolio Management Plan, being the master document for managing the portfolio, must be updated comprehensively. This includes revising the Portfolio Organizational Structure to align with new strategic goals, updating the Communication and Performance Management plans to reflect new objectives and reporting requirements, and modifying the Stakeholder Engagement plan as the interests, influence, and composition of the stakeholder community may have changed. Therefore, all listed components of the plan would require review and potential updates.
A. This is only one part of the necessary updates; focusing solely on the organizational structure would be insufficient to manage the overall impact of the strategic change.
B. This is also an incomplete answer. While communication and performance are critical, other areas like structure and stakeholder engagement are also directly impacted.
C. This is an incomplete answer. Stakeholder engagement is crucial, but it is just one of several key areas within the portfolio management plan affected by a strategic shift.
1. Project Management Institute. (2018). The Standard for Portfolio Management (4th ed.). Section 5.2.3.1, Portfolio Management Plan. The plan is described as a collection of subsidiary plans (e.g., communication, performance, stakeholder engagement) that are integrated to manage the portfolio.
2. Project Management Institute. (2018). The Standard for Portfolio Management (4th ed.). Section 5.3.3, Monitor and Control Portfolio Performance. This section details how changes, including strategic ones, trigger updates to the portfolio management plan.
Keep practicing
Take the free PFMP practice test
Ten exam-style questions with answers and explanations, plus the exam facts and study guides.
More questions
Other PFMP practice questions
- Question 1For years, your aerospace company has been a leader in the development of sophisticated a…
- Question 2While managing the portfolio value, it is important to know the different roles of respon…
- Question 3Portfolio Governance Model is developed as part of the Portfolio management plan and defi…
- Question 4In a portfolio, data is an abundant asset, and managing the information aiming for a a be…
- Question 5You have scored the portfolio components and are analyzing the data in order to prioritiz…
- Question 6Some of your Stakeholders reported to you that they are not receiving status reports and …