A portfolio manager on one of the major sub-portfolios in your portfolio has tendered his resignation and gave you a 2 months notice. This unexpected change will require you to take immediate action with the governance board. Which of the following processes will be handling this situation?
Full set: 490 questionsThe resignation of a key sub-portfolio manager is a significant event impacting resource availability and leadership, which could jeopardize portfolio objectives. The "Provide Portfolio Oversight" process, executed by the governance body, is responsible for monitoring the portfolio environment and performance, ensuring resources are managed effectively, and making decisions to keep the portfolio on track. Engaging the governance board to address this leadership gap falls directly under their oversight responsibilities to ensure portfolio continuity and success.
A. Manage Portfolio Risk: While the resignation is a risk, the action of engaging the governance board for a leadership issue is a function of oversight, which is a broader governance activity.
C. Manage strategic change: This process deals with changes to the organization's strategy, not with operational resource issues like a manager's resignation.
D. Manage Supply & Demand: This process focuses on balancing resource capacity against component needs, but the immediate escalation to the governance board is an oversight function, not a tactical resource allocation task.
Project Management Institute. (2018). The Standard for Portfolio Management (4th ed.). Section 5.4, Provide Portfolio Oversight, p. 69. The text states that oversight activities include "Ensuring that resources are available and managed effectively."
Project Management Institute. (2018). The Standard for Portfolio Management (4th ed.). Figure 5-1, Portfolio Governance Management Overview, p. 62. This figure shows that oversight is a key process within the governance domain for monitoring and controlling the portfolio.
Keep practicing
Take the free PFMP practice test
Ten exam-style questions with answers and explanations, plus the exam facts and study guides.
More questions
Other PFMP practice questions
- Question 1For years, your aerospace company has been a leader in the development of sophisticated a…
- Question 2While managing the portfolio value, it is important to know the different roles of respon…
- Question 3Portfolio Governance Model is developed as part of the Portfolio management plan and defi…
- Question 4In a portfolio, data is an abundant asset, and managing the information aiming for a a be…
- Question 5You have scored the portfolio components and are analyzing the data in order to prioritiz…
- Question 6Some of your Stakeholders reported to you that they are not receiving status reports and …