Assume you are the corporate portfolio manager for your global organization. There is one portfolio at the corporate level, but other portfolios…

Full set: 490 questions
Assume you are the corporate portfolio manager for your global organization. There is one portfolio at the corporate level, but other portfolios supporting business units and core areas of the company. One of these portfolios involves manufacturing, and its number one program in terms of priorities is to implement an enterprise resource planning system. Since it is the number one ranked program in this portfolio, it is of interest at the corporate level, and you and your team provide reports on its progress monthly. You can see that:
Answer options
A: Since earned value is being used, at this point you report the ERP system will not meet its cost and schedule goals
B: Extensive training will be needed after the program is complete, and an infrastructure does not exist to support the ERP system Correct answer
C: Use of the ERP vendor has been underestimated, and a business case will be needed for increased funding
D: Inadequate, up-front financial planning was done when the business case was approved
Correct Answer:
B. Extensive training will be needed after the program is complete, and an infrastructure does not exist to support the ERP system
Explanation

A corporate portfolio manager's primary focus is on strategic alignment, value delivery, and ensuring the organization can successfully absorb the outcomes of its components to realize benefits. The finding that extensive training is needed and supporting infrastructure is missing (Option B) represents a significant risk to benefits realization. This is a strategic, portfolio-level concern that directly impacts the value proposition of the ERP program and requires portfolio-level attention to ensure the investment is not wasted.

Why Incorrect

A. This option makes an unstated assumption that earned value is being used and draws a specific conclusion about performance that is not supported by the scenario.
C. This is a program-level budget issue. While it would be reported to the portfolio manager, it is more tactical than the strategic issue of benefits realization.
D. This is a retrospective finding about the initial planning. The portfolio manager is more concerned with current and future risks to value delivery.

References

Project Management Institute. (2017). The Standard for Portfolio Management (4th ed.). Section 1.3, The Link Between Portfolio Management and Organizational Strategy and Objectives, p. 9. This section emphasizes that portfolio management ensures the organization can realize benefits from its investments.

Project Management Institute. (2017). The Standard for Portfolio Management (4th ed.). Section 6.3, Authorize Portfolio, p. 89. This process group ensures that components are aligned with organizational capacity and capability to deliver value. Option B highlights a gap in this area.