PFMP practice question 28 of 35
Assume the organization's strategy has undergone a significant change, and as a result the mix of components in the portfolio also will change. As the portfolio manager, you need to update your charter in order to reflect:
Full set: 490 questionsThe portfolio charter is the official document that authorizes the portfolio's existence and provides the portfolio manager with the authority to apply resources. When organizational strategy changes significantly, the power structures, sponsors, and key decision-makers related to the new strategy often change as well. Updating the key stakeholders, especially the portfolio sponsor, is critical to ensure the portfolio remains formally authorized and aligned with the new leadership and their strategic vision. Without the correct authorizing stakeholders, the charter loses its legitimacy.
A. The new 'to be' vision: While the vision must also be updated, the charter's primary function is authorization, which is granted by stakeholders. An updated vision without the backing of the correct stakeholders is ineffective.
B. Interdependencies between the new components: This level of detail belongs in the portfolio management plan or supporting documents, not the high-level charter which focuses on authorization and strategic linkage.
C. Risk tolerances: Risk tolerances are typically detailed within the portfolio risk management plan. While high-level risk appetite may be mentioned, it's a less critical charter update than ensuring proper authorization.
1. Project Management Institute. (2018). The Standard for Portfolio Management (4th ed.). Section 4.1, Develop Portfolio Charter, p. 42. The standard specifies that the charter "formally authorizes the portfolio" and identifies "key stakeholders, roles, and responsibilities."
2. Project Management Institute. (2018). The Standard for Portfolio Management (4th ed.). Section 4.1.2.3, Portfolio Charter, p. 44. This section lists "Key stakeholders, roles, and responsibilities" as a key component of the charter.
Keep practicing
Take the free PFMP practice test
Ten exam-style questions with answers and explanations, plus the exam facts and study guides.
More questions
Other PFMP practice questions
- Question 1For years, your aerospace company has been a leader in the development of sophisticated a…
- Question 2While managing the portfolio value, it is important to know the different roles of respon…
- Question 3Portfolio Governance Model is developed as part of the Portfolio management plan and defi…
- Question 4In a portfolio, data is an abundant asset, and managing the information aiming for a a be…
- Question 5You have scored the portfolio components and are analyzing the data in order to prioritiz…
- Question 6Some of your Stakeholders reported to you that they are not receiving status reports and …