PFMP practice question 27 of 35
Assume at this point as the portfolio manager in your mattress company, you are activating portfolio components, updating portfolio reports, and documenting the decisions made at the recent Portfolio Governance Committee meeting as the company moves into new markets. You are therefore:
Full set: 490 questionsThe described activities—activating portfolio components, updating reports, and documenting governance decisions—are core tasks within the Authorizing and Controlling Process Group of the portfolio management lifecycle. "Activating portfolio components" is a direct result of the authorization process, where resources are officially committed to begin work on selected components. The reporting and documentation tasks are concurrent activities that support and formalize the authorization. Therefore, the portfolio manager is engaged in the overarching process of authorizing the portfolio, which translates strategic decisions into executable work.
A. Communicating decisions is a part of the process, but "authorizing the portfolio" is the comprehensive process group that includes this and other actions described.
B. Maintaining a decision log is a specific administrative task within the overall process, not the process itself. It is an input/output, not the primary action.
C. Updating the portfolio strategic plan is a strategic planning activity, which typically precedes the authorization of components based on that plan.
1. Project Management Institute. (2017). The Standard for Portfolio Management (4th ed.). Section 3, Figure 3-3, Portfolio Management Process Groups and Knowledge Areas, p. 26. This figure shows "Authorize Portfolio" as a key process within the Authorizing and Controlling Process Group.
2. Project Management Institute. (2017). The Standard for Portfolio Management (4th ed.). Section 4.3, Authorize Portfolio, p. 49. "Authorize Portfolio is the process of communicating portfolio component selection decisions and allocating financial and human resources to execute the portfolio."
Keep practicing
Take the free PFMP practice test
Ten exam-style questions with answers and explanations, plus the exam facts and study guides.
More questions
Other PFMP practice questions
- Question 1For years, your aerospace company has been a leader in the development of sophisticated a…
- Question 2While managing the portfolio value, it is important to know the different roles of respon…
- Question 3Portfolio Governance Model is developed as part of the Portfolio management plan and defi…
- Question 4In a portfolio, data is an abundant asset, and managing the information aiming for a a be…
- Question 5You have scored the portfolio components and are analyzing the data in order to prioritiz…
- Question 6Some of your Stakeholders reported to you that they are not receiving status reports and …