PFMP practice question 26 of 35

Having worked in portfolio management before, you are pleased you were selected to implement it and be the portfolio manager for your motorcycle…

Full set: 490 questions
Having worked in portfolio management before, you are pleased you were selected to implement it and be the portfolio manager for your motorcycle company, well known throughout the world. As it is a new function, you worked with the Enterprise Program Management Office to ensure you had a complete inventory of the work in progress. Now as you prepared your various portfolio management artifacts, and have a Portfolio Review Board meeting upcoming in two weeks, sponsors will be proposing new components. This means:
Answer options
A: A master schedule of resource allocation is needed
B: The meeting also should focus on reviewing existing components to see if they are aligned with current strategy Correct answer
C: People throughout the organization should know about this meeting and its decisions
D: The meeting should have a set agenda, and each member should be contacted before it to learn of key issues
Correct Answer:
B. The meeting also should focus on reviewing existing components to see if they are aligned with current strategy
Explanation

The primary purpose of a Portfolio Review Board (PRB) meeting is to govern the portfolio to ensure it remains aligned with organizational strategy. When new components are proposed, they must be evaluated not in isolation, but in the context of the entire portfolio. This necessitates a concurrent review of existing components to confirm their continued strategic alignment, value contribution, and fit within the newly proposed portfolio mix. This holistic review allows the PRB to make informed decisions about authorizing new work, re-prioritizing, or even terminating existing components to optimize the portfolio's value and maintain strategic alignment.

Why Incorrect

A. A master schedule of resource allocation is an output of portfolio component selection and authorization, not a prerequisite for the review meeting itself.
C. While communication is important, informing the entire organization is a broader communication plan activity, not the immediate focus of the PRB meeting's core purpose.
D. A set agenda and pre-meeting contact are standard meeting management practices, not the substantive portfolio management function being performed.

References

1. Project Management Institute. (2018). The Standard for Portfolio Management (4th ed.). Section 5.4.3, Portfolio Review Meetings, p. 62. "Portfolio review meetings are held to monitor the portfolio performance and make decisions... This includes... authorizing new portfolio components... and reevaluating existing portfolio components to confirm their continued contribution to the portfolio’s strategic objectives."

2. Project Management Institute. (2018). The Standard for Portfolio Management (4th ed.). Section 6.4, Optimize Portfolio, p. 78. "Portfolio optimization is the activity of evaluating, selecting, prioritizing, and balancing portfolio components to ensure alignment with the organizational strategy and objectives."