PFMP practice question 25 of 35

Working to monitor the portfolio especially in terms of its value to the organization, you had each component manager prepare monthly variance reports. Of the components ranked in the top 10, six of them realized they would not require some of their initial funding and still would be completed as planned. This means:

Full set: 490 questions
Answer options
A: Three-point estimating should be used as funds are allocated
B: Next year's budget can be adjusted Correct answer
C: Historical data would be useful on estimates versus actual costs
D: The amount of contingency and management reserves can be decreased
Correct Answer:
B. Next year's budget can be adjusted
Explanation

The variance reports show that multiple high-priority components are underspending their budgets. This information provides a real-time, data-driven insight into the portfolio's financial performance against its plan. At the portfolio level, this aggregate financial data is a critical input for future planning cycles. The most direct and strategic use of this information is to adjust the financial forecasts and budget for the next fiscal year. This allows the organization to optimize its capital allocation based on demonstrated performance, potentially freeing up funds for other strategic initiatives or reducing overall spending.

Why Incorrect

A. Three-point estimating is a specific technique; the scenario does not provide enough detail to conclude it is the necessary solution.
C. The scenario is providing historical data (variance reports); stating that it would be useful is redundant, not an action.
D. The surplus is in component operational funding, not necessarily contingency reserves, so decreasing reserves is an unsubstantiated leap.

References

1. Project Management Institute. (2017). The Standard for Portfolio Management (4th ed.). Section 6.2, Monitor and Control Portfolio Performance, p. 84. "Performance monitoring involves collecting, measuring, and disseminating performance information... to provide feedback for future planning cycles."

2. Project Management Institute. (2017). The Standard for Portfolio Management (4th ed.). Section 6.2.2, Monitor and Control Portfolio Performance: Tools and Techniques, p. 87. This section lists variance analysis as a key tool, noting that outputs include "forecasts" and "change requests," which directly inform future budget adjustments.

Scroll to Top