PFMP practice question 32 of 35
Assume your food additive company performed a capacity analysis and found some resources had not maintained their skill sets and basically were not…
Full set: 490 questionsThe portfolio selection process must prioritize components based on strategic importance, urgency, and risk. The new government regulation requiring an additional FDA quality check represents a mandatory compliance requirement. Failure to address this could result in legal penalties, operational shutdowns, and significant financial losses, posing a major risk to the entire organization. Therefore, the component to add staff and processes to meet this regulatory demand (Component B) should take precedence over discretionary strategic initiatives like acquisitions (C), internal improvements (A), or infrastructure upgrades (D), which can be scheduled with more flexibility.
A. Enhancing morale is an important outcome but is less urgent and tangible than a mandatory regulatory requirement with severe non-compliance penalties.
C. Acquiring a competitor is a strategic growth option but is discretionary and carries its own risks, unlike a non-negotiable compliance mandate.
D. Infrastructure upgrades are important for long-term operations but are likely less time-critical than a newly imposed, mandatory government regulation.
1. Project Management Institute. (2017). The Standard for Portfolio Management (4th ed.). Section 5.2.2, p. 60. Discusses component categorization, noting that categories can include "regulatory" or "compliance." Such components are often mandatory and prioritized accordingly.
2. Project Management Institute. (2017). The Standard for Portfolio Management (4th ed.). Section 6.4, p. 87. "Portfolio risk management includes the identification of risks that may impact the ability of the portfolio to achieve its strategic objectives." A new regulation is a significant portfolio-level risk.
3. Cooper, R. G., Edgett, S. J., & Kleinschmidt, E. J. (2001). Portfolio management for new product development: results of an industry practices study. R&D Management, 31(4), 361-380. https://doi.org/10.1111/1467-9310.00225 (Highlights that portfolios often contain a mix of project types, including mandatory projects that must be funded).
Keep practicing
Take the free PFMP practice test
Ten exam-style questions with answers and explanations, plus the exam facts and study guides.
More questions
Other PFMP practice questions
- Question 1For years, your aerospace company has been a leader in the development of sophisticated a…
- Question 2While managing the portfolio value, it is important to know the different roles of respon…
- Question 3Portfolio Governance Model is developed as part of the Portfolio management plan and defi…
- Question 4In a portfolio, data is an abundant asset, and managing the information aiming for a a be…
- Question 5You have scored the portfolio components and are analyzing the data in order to prioritiz…
- Question 6Some of your Stakeholders reported to you that they are not receiving status reports and …