PFMP practice question 31 of 35

You have a portfolio component that is using earned value analysis. It is at the 15% point of completion, and it is evident that it cannot be…

Full set: 490 questions
You have a portfolio component that is using earned value analysis. It is at the 15% point of completion, and it is evident that it cannot be completed as planned. Adding resources will not solve the problem, and at the last Portfolio Review Board meeting, the Board members decided to terminate this component based on its various risks. They then decided the resources allocated to this component could be transferred to other portfolio components enhancing their early completion and avoiding risks from competitors. As the portfolio manager, you:
Answer options
A: Worked with the component managers to ease the transition
B: Documented these decisions in portfolio reports Correct answer
C: Set up both quantitative and qualitative metrics to determine the usefulness of adding resources to the other components
D: Met with the affected component managers and their teams to explain these changes
Correct Answer:
B. Documented these decisions in portfolio reports
Explanation

The Portfolio Review Board, as the governing body, has made a formal decision to terminate one component and reallocate its resources. The portfolio manager's primary and immediate responsibility following a governance decision is to ensure it is officially recorded and communicated. Documenting these decisions in portfolio reports creates an official record, ensures transparency, provides a basis for all subsequent actions (like transitioning resources), and maintains the integrity of the portfolio governance process. This formal documentation is the foundation for executing the board's directive.

Why Incorrect

A. This is a subsequent implementation step that follows the formal documentation and communication of the decision.
C. This analysis should have been performed before the Board made its decision, to provide them with the data needed to make an informed choice.
D. This is an important communication and change management activity, but it is enabled by and follows the official documentation of the decision.

References

1. Project Management Institute. (2017). The Standard for Portfolio Management (4th ed.). Section 3.2, Portfolio Governance. This section emphasizes the role of the governance body in making decisions and the portfolio manager's role in facilitating and documenting these decisions.

2. Project Management Institute. (2017). The Standard for Portfolio Management (4th ed.). Section 7.3, Monitor and Control Portfolio Performance. This process includes generating performance reports that document status, progress, and key decisions made.