Embracing a management-by-projects culture means there tends to be far more projects to pursue than available resources. An approach then is required to guide decisions as to components in the portfolio. A best practice to follow is to:
Full set: 490 questionsWhen project demand exceeds resource capacity, a structured and objective approach is essential for selection. A prioritization model, defined within the portfolio strategic plan, provides this approach. It uses predefined criteria, often weighted and scored, to evaluate and rank potential components based on their alignment with strategic objectives, value, risk, and resource constraints. This ensures that the most valuable components are selected, optimizing the use of limited resources and maximizing strategic contribution.
B. A portfolio roadmap is a visual timeline of selected components; it is an output of prioritization, not the tool used to perform it.
C. Analyzing environmental changes is a critical input for strategic planning and risk assessment, but it is not the prioritization approach itself.
D. Sustaining project benefits is a key consideration and a criterion within a prioritization model, but it is not the overarching best-practice approach for selection.
1. Project Management Institute. (2018). The Standard for Portfolio Management (4th ed.). Section 5.3, Develop Portfolio Strategic Plan, p. 60. "The portfolio strategic plan documents the organization’s strategic goals and objectives... It also defines how portfolio components will be evaluated, selected, prioritized, and balanced..."
2. Project Management Institute. (2018). The Standard for Portfolio Management (4th ed.). Section 6.3, Prioritize Portfolio Components, p. 79. "Prioritizing portfolio components is the process of ranking components based on a predefined evaluation model or criteria."
3. Cooper, R. G., Edgett, S. J., & Kleinschmidt, E. J. (2001). Portfolio Management for New Products: Second Edition. Basic Books. (While focused on new products, this foundational text extensively covers the necessity of formal scoring and prioritization models for effective portfolio selection under resource constraints, a principle adopted by PMI).
Keep practicing
Take the free PFMP practice test
Ten exam-style questions with answers and explanations, plus the exam facts and study guides.
More questions
Other PFMP practice questions
- Question 1For years, your aerospace company has been a leader in the development of sophisticated a…
- Question 2While managing the portfolio value, it is important to know the different roles of respon…
- Question 3Portfolio Governance Model is developed as part of the Portfolio management plan and defi…
- Question 4In a portfolio, data is an abundant asset, and managing the information aiming for a a be…
- Question 5You have scored the portfolio components and are analyzing the data in order to prioritiz…
- Question 6Some of your Stakeholders reported to you that they are not receiving status reports and …