Gary is the project manager of the GHY project. He has elected to use a previous, but similar, project to guide him and the project team through the estimate activity duration process. The previous project schedule could best described as which one of the following?
Full set: 327 questionsThis is an example of an organizational process asset. The previous project is the historical information that the current project can use. This could also be, with a bit more information, an example of an analogous estimate. Organizational process assets are forms, templates, and other support pieces that the project managers can use to help manage their projects. It is usually something that has been created before the project begins and often, but not always, comes from historical information. Answer option D is incorrect. This is not a valid term for this question. Answer option B is incorrect. The lessons learned documentation is a separate document that Gary might reference for his current project, but this is not a valid choice. Answer option C is incorrect. While organizational process assets are inputs to this process, this choice is not the best selection for the question.
Keep practicing
Take the free PMI-SP practice test
Ten exam-style questions with answers and explanations, plus the exam facts and study guides.
More questions
Other PMI-SP practice questions
- Question 2Which of the following are the inputs to the Develop Project Charter process? Each correc…
- Question 4You are the project manager of the GHT Project. Ben, one of your project team members, do…
- Question 5Harry works as a project manager for BlueWell Inc. He is determining the budget of the pr…
- Question 6Holly is the project manager for her organization. In her project, she has worked with th…
- Question 7Joe is the project manager of the HJN Project. Joe's project is a renovation of an office…
- Question 8The Define Activities process is the first process in the project time management knowled…