PMI-SP practice question 32 of 35

John works as the project manager for Blue Well Inc. He is identifying the phases within the scope of work for the project plan. Which of the following can be categorized as a project phase? Each correct answer represents a complete solution. Choose all that apply.

Full set: 327 questions
Answer options
A: Concrete
B: Pre-construction
C: Engineering
D: Conceptual engineering
Correct Answer:
s C, D, and B.
Explanation

A phase is a combination of associated activities that represent a distinct stage within a project. A phase can have distinct start and finish dates and include several stages of planning and work. Each project has a defined scope of work, such as a unique product or service. Some examples of phases within the scope of work for a project plan are conceptual engineering, pre- construction, and engineering. Answer option A is incorrect. Concrete is an activity, not a project phase.