PMI-SP practice question 32 of 35
John works as the project manager for Blue Well Inc. He is identifying the phases within the scope of work for the project plan. Which of the following can be categorized as a project phase? Each correct answer represents a complete solution. Choose all that apply.
Full set: 327 questionsCorrect Answer:
s C, D, and B.
Explanation
A phase is a combination of associated activities that represent a distinct stage within a project. A phase can have distinct start and finish dates and include several stages of planning and work. Each project has a defined scope of work, such as a unique product or service. Some examples of phases within the scope of work for a project plan are conceptual engineering, pre- construction, and engineering. Answer option A is incorrect. Concrete is an activity, not a project phase.
Keep practicing
Take the free PMI-SP practice test
Ten exam-style questions with answers and explanations, plus the exam facts and study guides.
More questions
Other PMI-SP practice questions
- Question 2Which of the following are the inputs to the Develop Project Charter process? Each correc…
- Question 4You are the project manager of the GHT Project. Ben, one of your project team members, do…
- Question 5Harry works as a project manager for BlueWell Inc. He is determining the budget of the pr…
- Question 6Holly is the project manager for her organization. In her project, she has worked with th…
- Question 7Joe is the project manager of the HJN Project. Joe's project is a renovation of an office…
- Question 8The Define Activities process is the first process in the project time management knowled…