PMI-SP practice question 33 of 35

You are the project manager of the NHQ project. This project is slightly larger than the GTR project, in which you also served as the project…

Choose your answer, then check it against the explanation.

You are the project manager of the NHQ project. This project is slightly larger than the GTR project, in which you also served as the project manager. You decide to use the actual activity duration of the GTR project as a basis for your current NHQ project. This, you reason, will save time for your project, as the previous project has provided the information. Which one of the following terms best describes the action you are doing in this scenario?
Answer options
Question 33 of 35

Keep practicing

Take the free PMI-SP practice test

Ten exam-style questions with answers and explanations, plus the exam facts and study guides.

Start the free practice test

More questions

Other PMI-SP practice questions

Scroll to Top