PMI-SP practice question 33 of 35
You are the project manager of the NHQ project. This project is slightly larger than the GTR project, in which you also served as the project…
Full set: 327 questionsThis is an example of analogous estimate as you are creating an analogy between two similar projects. This estimating approach is also known as a top-down estimate type, and is somewhat unreliable. Answer option C is incorrect. Expert judgment relies on experts, consultants, or subject matter experts to guide your project decisions. An analogous estimate is a form of expert judgment, but this is not the best choice for this question. Answer option B is incorrect. A bottom-up estimate creates an activity duration estimate for each work package in the WBS. It is the longest estimate type to create, but it also the most reliable. Answer option D is incorrect. A rough order of magnitude estimate is a quick estimate, usually for project costs, that often has a broad range of variance attached to the estimate.
Keep practicing
Take the free PMI-SP practice test
Ten exam-style questions with answers and explanations, plus the exam facts and study guides.
More questions
Other PMI-SP practice questions
- Question 2Which of the following are the inputs to the Develop Project Charter process? Each correc…
- Question 4You are the project manager of the GHT Project. Ben, one of your project team members, do…
- Question 5Harry works as a project manager for BlueWell Inc. He is determining the budget of the pr…
- Question 6Holly is the project manager for her organization. In her project, she has worked with th…
- Question 7Joe is the project manager of the HJN Project. Joe's project is a renovation of an office…
- Question 8The Define Activities process is the first process in the project time management knowled…
