PMI-SP practice question 33 of 35
You are the project manager of the NHQ project. This project is slightly larger than the GTR project, in which you also served as the project…
Choose your answer, then check it against the explanation.
You are the project manager of the NHQ project. This project is slightly larger than the GTR project,
in which you also served as the project manager. You decide to use the actual activity duration of the
GTR project as a basis for your current NHQ project. This, you reason, will save time for your project,
as the previous project has provided the information. Which one of the following terms best
describes the action you are doing in this scenario?
Question 33 of 35
Keep practicing
Take the free PMI-SP practice test
Ten exam-style questions with answers and explanations, plus the exam facts and study guides.
More questions
Other PMI-SP practice questions
- Question 2Which of the following are the inputs to the Develop Project Charter process? Each correc…
- Question 4You are the project manager of the GHT Project. Ben, one of your project team members, do…
- Question 5Harry works as a project manager for BlueWell Inc. He is determining the budget of the pr…
- Question 6Holly is the project manager for her organization. In her project, she has worked with th…
- Question 7Joe is the project manager of the HJN Project. Joe's project is a renovation of an office…
- Question 8The Define Activities process is the first process in the project time management knowled…
