PMI-SP practice question 34 of 35
There are seven inputs to the estimate activity durations process. Which one of the following is NOT an input to this process?
Full set: 327 questionsCorrect Answer:
A. Scope baseline
Explanation
The scope baseline is not an input to the estimate activity durations process. The project's scope statement is an input, but according to the PMBOK, the scope baseline is not. The seven inputs to this process are: activity list, activity attributes, activity resource requirements, resource calendars, project scope statement, enterprise environmental factors, and organizational process assets. Answer options C, B, and D are incorrect. These all are an input to the estimate activity durations process.
Keep practicing
Take the free PMI-SP practice test
Ten exam-style questions with answers and explanations, plus the exam facts and study guides.
More questions
Other PMI-SP practice questions
- Question 2Which of the following are the inputs to the Develop Project Charter process? Each correc…
- Question 4You are the project manager of the GHT Project. Ben, one of your project team members, do…
- Question 5Harry works as a project manager for BlueWell Inc. He is determining the budget of the pr…
- Question 6Holly is the project manager for her organization. In her project, she has worked with th…
- Question 7Joe is the project manager of the HJN Project. Joe's project is a renovation of an office…
- Question 8The Define Activities process is the first process in the project time management knowled…
