PMI-SP practice question 11 of 35

Vicky is the project sponsor of Robert's project. She has requested several changes for the project scope and these changes have, of course, been…

Choose your answer, then check it against the explanation.

Vicky is the project sponsor of Robert's project. She has requested several changes for the project scope and these changes have, of course, been approved. Robert needs to incorporate the project scope changes into the activity list. Where else should Robert reflect these project changes?
Answer options
Question 11 of 35

Keep practicing

Take the free PMI-SP practice test

Ten exam-style questions with answers and explanations, plus the exam facts and study guides.

Start the free practice test

More questions

Other PMI-SP practice questions

Scroll to Top