PMI-SP practice question 12 of 35
You have been hired as a contract project manager for Tech Perfect Inc. The project has already been started. Sufficient details of the project have already been structured. You are working with your team for cost estimation of the project. Which of the following estimating techniques will you use for the highest degree of accuracy?
Full set: 327 questionsAccording to the question, you have to use the estimating technique that has a higher degree of accuracy. The most accurate estimating technique is bottom-up estimating. What is bottom-up estimating? Bottom-up is a cost estimating technique that involves estimating the cost of individual work packages or schedule activities with the lowest level of detail. The detailed cost is rolled up (or summarized) to higher levels for total project estimates. This summarized data is very useful for reporting and tracking purposes. Bottom-up estimating provides a higher degree of accuracy, provided the estimates at the work package level are accurate. Answer options C, A, and B are incorrect. Parametric modeling and analogous estimating techniques use top-down estimation model. These are less accurate than the bottom-up estimation. What is analogous estimating? Analogous is an estimating technique that uses the values of parameter, such as scope, cost, budget, and duration or measures of scale such as size, weight, and complexity from a previous, similar activity as the basis for estimation of the same parameter for a future activity. It is a top-down estimating technique and is a form of expert judgment. It provides a lower degree of accuracy than other estimating techniques. This technique is primarily used when there is a limited amount of detailed information about the project or program. What is parametric modeling? Parametric modeling is an estimating technique that uses parameters, or project characteristics, to forecast project costs. It involves a top-down approach and is similar but more accurate than analogous estimating. It uses historical data and other variables to calculate an estimate for activity parameters, such as scope, cost, budget, and duration.
Keep practicing
Take the free PMI-SP practice test
Ten exam-style questions with answers and explanations, plus the exam facts and study guides.
More questions
Other PMI-SP practice questions
- Question 2Which of the following are the inputs to the Develop Project Charter process? Each correc…
- Question 4You are the project manager of the GHT Project. Ben, one of your project team members, do…
- Question 5Harry works as a project manager for BlueWell Inc. He is determining the budget of the pr…
- Question 6Holly is the project manager for her organization. In her project, she has worked with th…
- Question 7Joe is the project manager of the HJN Project. Joe's project is a renovation of an office…
- Question 8The Define Activities process is the first process in the project time management knowled…