PMI-SP practice question 30 of 35
You are the project manager for the NHQ project. The management has reminded you that you must not allocate any project team member for more than 25…
Choose your answer, then check it against the explanation.
You are the project manager for the NHQ project. The management has reminded you that you must
not allocate any project team member for more than 25 hours per work week on your project. This
policy is because your organization is in a weak matrix and the project team members are on several
projects at once within the organization. The 25-hour limit per resource is an example of which one
of the following?
Question 30 of 35
Keep practicing
Take the free PMI-SP practice test
Ten exam-style questions with answers and explanations, plus the exam facts and study guides.
More questions
Other PMI-SP practice questions
- Question 2Which of the following are the inputs to the Develop Project Charter process? Each correc…
- Question 4You are the project manager of the GHT Project. Ben, one of your project team members, do…
- Question 5Harry works as a project manager for BlueWell Inc. He is determining the budget of the pr…
- Question 6Holly is the project manager for her organization. In her project, she has worked with th…
- Question 7Joe is the project manager of the HJN Project. Joe's project is a renovation of an office…
- Question 8The Define Activities process is the first process in the project time management knowled…
