PMI-SP practice question 30 of 35

You are the project manager for the NHQ project. The management has reminded you that you must not allocate any project team member for more than 25…

Choose your answer, then check it against the explanation.

You are the project manager for the NHQ project. The management has reminded you that you must not allocate any project team member for more than 25 hours per work week on your project. This policy is because your organization is in a weak matrix and the project team members are on several projects at once within the organization. The 25-hour limit per resource is an example of which one of the following?
Answer options
Question 30 of 35

Keep practicing

Take the free PMI-SP practice test

Ten exam-style questions with answers and explanations, plus the exam facts and study guides.

Start the free practice test

More questions

Other PMI-SP practice questions

Scroll to Top