PMI-SP practice question 30 of 35
You are the project manager for the NHQ project. The management has reminded you that you must not allocate any project team member for more than 25…
Full set: 327 questionsThe limit on each work is an organizational policy for each project. Policies, rules, and organizational requirements are the enterprise environmental factors. Answer option D is incorrect. Organizational process assets are things that have been created for the project manager, such as software, templates, guidelines, and other resources that will assist the project manager in completing the project. Answer option C is incorrect. While this could be a resource limitation, it is not a valid project management term. Resource leveling heuristics or a project constraint would have been acceptable answers. Answer option A is incorrect. Expert judgment happens, when the project manager relies on someone with more knowledge on a topic to help the project manager make the best project decision.
Keep practicing
Take the free PMI-SP practice test
Ten exam-style questions with answers and explanations, plus the exam facts and study guides.
More questions
Other PMI-SP practice questions
- Question 2Which of the following are the inputs to the Develop Project Charter process? Each correc…
- Question 4You are the project manager of the GHT Project. Ben, one of your project team members, do…
- Question 5Harry works as a project manager for BlueWell Inc. He is determining the budget of the pr…
- Question 6Holly is the project manager for her organization. In her project, she has worked with th…
- Question 7Joe is the project manager of the HJN Project. Joe's project is a renovation of an office…
- Question 8The Define Activities process is the first process in the project time management knowled…
