PMI-SP practice question 27 of 35
Your project team has identified a project risk that must be responded to. The risk has been recorded in the risk register and the project team has been discussing potential risk responses for the risk event. The event is not likely to happen for several months but the probability of the event is high. Which one of the following is a valid response to the identified risk event?
Full set: 327 questionsCorrect Answer:
D. Corrective action
Explanation
Corrective actions include contingency plans and workaround plans, which are valid risk responses. Answer option B is incorrect. The technical performance measurement may be part of the analysis of the risk, but not part of the response. Answer option A is incorrect. A risk audit may be appropriate once the risk event and response has been identified. Answer option C is incorrect. The impact of the risk event may affect earned value management calculations, but EVM in and of itself is not a valid risk response.
Keep practicing
Take the free PMI-SP practice test
Ten exam-style questions with answers and explanations, plus the exam facts and study guides.
More questions
Other PMI-SP practice questions
- Question 2Which of the following are the inputs to the Develop Project Charter process? Each correc…
- Question 4You are the project manager of the GHT Project. Ben, one of your project team members, do…
- Question 5Harry works as a project manager for BlueWell Inc. He is determining the budget of the pr…
- Question 6Holly is the project manager for her organization. In her project, she has worked with th…
- Question 7Joe is the project manager of the HJN Project. Joe's project is a renovation of an office…
- Question 8The Define Activities process is the first process in the project time management knowled…